The 8” line had suffered from internal corrosion at the elbow.


NATURE OF DEFECT
The 8” line had suffered from internal corrosion at the elbow. This resulted in significant wall loss. The client requires a composite repair to account for a through wall defect at that location. Metalyte Pipeworks have produced a repair method using Herculyte epoxies to help mitigate the defects with a minimum overwrap of 18 layers on the 8” and 4 layers on the 32” of Dragon-Q-UHT composite

SOLUTION
Metalyte Pipeworks produced a repair method using Herculyte epoxies to resolve the defects with a minimum overwrap of 18 layers and 4 layers of Dragon-Q-UHT composite system.

REPAIR METHOD
The substrate was prepared (excluding the identified defect area) using shot blasting to a surface profile of SA2.5.
500 microns of Dragon resin was applied as a bonding coat to the entire repair area prior to applica- tion of the Dragon composite and the repair area was wrapped in 18 layers and 4 layers of engi- neered Dragon-Q-UHT composite system and allowed to cure until a minimum of 74.5 “Shore D” hardness was achieved.