MP Case History

48 Inch Sea Water Line

The 48” Cooling Water line had suffered from external and internal corrosion.

Nature of defect

The 48” Cooling Water line had suffered from external and internal corrosion. This resulted in a large through-wall defect at the 12 o clock position. Adjacent to the leak was a second corroded section approximately 500mm away. After surface preparation was complete, the second location also produced a leak. The client required a composite repair to seal the leak locations and to bring the line back up to its full design specification.

There was a 4-metre section adjacent to the above section that also required a repair. Several areas within this section had suffered from external corrosion resulting in an expected RWT reading of 1mm.

Solution

Metalyte Pipeworks solution was to install a repair, initially using Herculyte epoxies and a pre formed steel plate to seal the defects with a minimum overwrap of 10 layers of Dragon-Q-UHT composite.

Repair method

The full repair area of 8 metres was prepped by on site shot blasters to Sa 2.5 with a minimum surface roughness of 55 microns. The Metalyte Pipeworks team then installed the cold bonded epoxy plates over the through wall defects. Any areas of wall loss were repaired using a high compression load transfer paste.

The cold bonded plates and load transfer paste was allowed to cure before the Dragon composite was applied. A total of 10 layers was applied over the 8 metre area to bring the line back up to full design specification. Once the composite was fully cured and tested, the Metalyte technicians applied 2 coats of UV resistant protection.

Recent Case Histories